Construction Updates

Information regarding the construction project:

   – Title: 2022 FAA Airport Capital Improvement Plan Project

   – $6.3M Construction will begin April 3rd, 2023

   – It will consist of 3-60 day phases

   – 1st Phase (Red) – April and May, TWY J, T-Hangar Taxilanes, and overflow apron

   – 2nd Phase (Blue) – June and July, TWY H, L, and N

   – 3rd Phase (Green) – August and September, TWY G, M, and small section of N

   – TWY A will have 21 day closures at the beginning of Phases 1&3

   – CHECK NOTAMs for most current closures