Information regarding the construction project:
– Title: 2022 FAA Airport Capital Improvement Plan Project
– $6.3M Construction will begin April 3rd, 2023
– It will consist of 3-60 day phases
– 1st Phase (Red) – April and May, TWY J, T-Hangar Taxilanes, and overflow apron
– 2nd Phase (Blue) – June and July, TWY H, L, and N
– 3rd Phase (Green) – August and September, TWY G, M, and small section of N
– TWY A will have 21 day closures at the beginning of Phases 1&3
– CHECK NOTAMs for most current closures